Accelerated Plant Shutdown

twitter
linkedin
facebook

The Challenge

opportunities-project-planning

Problem

• Summer shutdown maintenance with many inefficiencies and a lack of standards

• High manpower costs (80 external resources)

• Long duration (3 weeks)

Root Causes

• Spares/tools not ordered in advance

• Critical Plan not visible

• Tasks planned with a lot of safety (buffer)

• Little time invested in task and resource planning

The solution

mission-control-meeting-plant-shutdown

• Pull Planning with Time and Cost Buffers

• Visual Management Boards for work and KPI monitoring

• Spare parts stored near machines, and tool/consumable kits prepared

• Daily cost control

The Results

The project resulted in Annual Savings of £2.5 million.

manpower-cost-reduction-benefits

Manpower cost reduction

Manpower costs reduced by 25%

shutdown-duration-benefits

Shutdown duration

Shutdown duration reduced by 10%

#process manufacturing #research and development #maintenance

See more on Process Manufacturing

Find out more about transformation in this sector

See more on Maintenance

Find out more about improving this business area

Get the latest news about Kaizen Institute